Southfield Road boulevard plan moves to design; construction is years away

Southfield will pay $350,000 toward engineering for a six-lane boulevard from Mount Vernon to 13 Mile, a project talked about for some 25 years. Construction, which isn't funded yet, would come in 2030 or 2031.

By OCJ Staff

Published

Oakland County Journal Traffic Update graphic

A long-discussed plan to turn Southfield Road into a six-lane boulevard has taken a step forward, though drivers won't see construction for years.

The Southfield City Council on Sept. 22 approved a cost-sharing agreement with the Road Commission for Oakland County to pay for engineering and design, C&G Newspapers' Southfield Sun reported. The vote tally was not reported.

The money

Design and engineering are expected to cost $3.5 million:

  • Federal Surface Transportation Program money covers $2.8 million.
  • The Road Commission and the city split the remaining $700,000 — $350,000 each. Southfield's share comes from its major streets budget.

Construction is not funded and would need a separate approval later.

The project

The plan calls for a six-lane boulevard with a median from Mount Vernon to 13 Mile Road. Southfield's portion runs from Mount Vernon to Lincoln Drive. The idea has been discussed for about 25 years.

The expected timeline:

  • Design: fiscal years 2027-28
  • Right-of-way: fiscal years 2028-30
  • Construction: 2030 or 2031

Mayor Kenson Siver said the road as it is "really divides the community," according to the Sun. Councilwoman Yolanda Haynes raised concerns about people soliciting on the median.

This story uses reporting from C&G Newspapers.

Filed under: Southfield, Southfield Road, Road Commission for Oakland County, roads, city council

The stories nobody else is covering, in your inbox

A free email with the latest from the Oakland County Journal. Unsubscribe any time.

We never sell or share your address. See our privacy policy.